-2020 ACTION PLAN
DEVELOPMENT DIMENSION: GOVERNANCE, CORRUPTION AND PUBLIC ACCOUNTABILITY
DEVELOPMENT DIMENSION: SOCIAL DEVELOPMENT
DEVELOPMENT DIMENSION: ECONOMIC DEVELOPMENT
GOAL 3: BUILD A PROSPEROUS SOCIETY | |||||||||||||||
dePROGRAMMES | SUB-PROGRAMMES | GLOBAL & REGIONAL LINK. | ACTIVITIES
|
LOCATION | BASELINE | OUTPUT INDICATORS | QUARTERLY TIME SCHEDULE | LOCATION | BASELINE | ||||||
1 | 2 | 3 | 4 | IGF | GOG
|
DONOR
|
LEAD | COLLAB. | |||||||
SDG 8,17
AU 4 |
Complete 1No. 16 unit lockable stores | Swedru
|
Limited access to economic opportunities | No. of lockable stores completed | x | x | x | x |
100,000.00 |
DA | DWD | ||||
SDG 8,17
AU 4 |
Construct 1 No. 10unit lockable stores | Awisa | Limited access to economic opportunities | No. of Lockable stores constructed | x | x | x | x | 3,000,000.00 | DA | DWD | ||||
Economic Development | SP4.1: Trade, Tourism and Industrial Development | SDG 1,8,
AU 1,4,5 |
Conduct public awareness on the benefits of co-operatives | District Wide | Limited access to information | No. of Public awareness organized | x | x | x | x | 2,000.00 | DSD | DA | ||
SDG 1,8,
AU 1,4,5 |
Train agro processing groups in managerial and technical skills | District Wide | Limited capacity of agro processing groups | No. of Agro processors assed and trained
|
x | x | x | x | 5,000.00 | DSD | DA | ||||
SDG 1,8,
AU 1,4,5 |
Form and train viable financial co-operative societies | District Wide | Defunct existing cooperative societies | No. of co-operatives formed and trained | x | x | x | x | 500.00
|
DA | |||||
Economic Development | SP4.1: Trade, Tourism and Industrial Development | SDG 1,8,
AU 1,4,5 |
Support District Chamber of Agriculture Commerce (EDC) and Technology Activities | District Wide | Dormant existing committee | Amount spent on DCACT activities | x | x | x | x | 50,000.00 | DCACT | DA | ||
Economic Development | SP4.1: Trade, Tourism and Industrial Development | SDG 1,2,7,9,17
AU 4,5,7,9 |
Create and Support District Agriculture Advisory Services (DAAS) to provide advice on productivity enhancing technologies | District Wide | DAAS non-existent | No. of DAAS created and No. of clients supported | x | x | x | x | 35,000.00 | DA | |||
Economic Development | SP4.1: Trade, Tourism and Industrial Development | SDG 1,2,7,9,17
AU 4,5,7,9 |
Identify and promote potential tourist sites in the District | District Wide | Limited avenues for tourist promotion | No. of tourist sites identified
No. of tourist sites promoted |
x | x | x | x | 10,000.00 | DA
|
DPCU
Assembly members |
||
Economic Development | SP4.2: Agricultural Development | SDG 1,2,7,9,17
AU 4,5,7,9 |
Support implementation of Planting for Food and Jobs programme | District Wide | 10,000 seedlings | Annual yield per hectare | x | x | x | x | 20,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 1,2,7,9,17
AU 4,5,7,9 |
Nurse 40,000 palm in selected communities
|
District Wide | Planting sites identified | No. of Seedlings nursed | x | x | x | x | 80,000.00 | Dept. of Agric | DA, | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Construct one Storage Facility to prevent post-harvest loss | Swedru | Lack of storage facilities | No. of Storage facility constructed | x | x | x | x | 400,000.00 | IPEP
DCACT Dept. of Agric |
DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Organize monthly Technical and Activity review meeting | District wide | Mandatory meetings | No. Technical activity review meetings organized | x | x | x | x | 2,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Hold District Annual Planning and Performance review/stakeholder meeting | District wide | Mandatory meetings | No. of meetings held | x | x | x | x | 5,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Purchase of Stationaries and Payment of Utility Bills | Swedru | Inadequate stationary | No. of stationeries purchased
Amount used |
x | x | x | x | 3,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Organize RELC planning sessions | Swedru | Improved planning and budgeting | No. of RELC planning sessions organized | x | x | x | x | 4,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Organize Forum on sustainable Land Management and Climate Change Agriculture | Swedru
|
Poor climate change practices | No. of forums organized | x | x | x | x | 5,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Collaborate with MMDAs, traders etc. to implement GAPs annually (Good Agriculture Practices). | Swedru | Application of Outmoded Agricultural practices | No. of MMDAs, traders collaborated
No. of GAPs implemented |
x | x | x | x | 5,000.00 | Dept. of Agric | DA | ||
Identify and train FBO leadership (at least 30% females) in CSA technologies | Swedru | Poor climate change practices | No. of FBOs identified and trained | x | x | x | x | 5,000.00 | Dept. of Agric | DA | |||||
Train farmers in dry season gardening | Swedru | Poor yield | No. of FBOs trained | x | x | x | x | 5,000.00 | Dept. of Agric | DA | |||||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Provide Training and Start up Kits for 500 youth on Grass cutter Rearing | District wide | Limited capacity and access to economic opportunities | No. of startup kits provided | x | x | x | x | 30,000.00 | Dept. of Agric | DA | ||
SDG 2,8,9,12
AU 5 |
Organize sensitization programs on HIV/AIDS, Child Labour, Occupational safety, Health & Environmental Issues | District wide | Low awareness created | No. of sensitization programs organized | x | x | x | x | 1125.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Demonstrate bud Manipulation Technique in plantain sucker multiplication | District wide | Poor yield | No. of bud manipulation technique demonstrated | x | x | x | x | 2500.00 | Dept. of Agric | DA | ||||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Conduct field demonstration on decapitation on plantain sucker multiplication | District wide | Poor yield | No. of field decapitation demonstrated | x | x | x | x | 1500.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Organize training in good agricultural practices for rice farming | District wide | Poor agricultural practices | No. of trainings organized | x | x | x | x | 4,800.00 | Dept. of Agric | DA | ||
SDG 2,8,9,12
AU 5 |
Train farmers on proper storage of grains using the hermetic poly bag | District wide | Improved food security
|
No. of farmers trained | x | x | x | x | 2,500.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Train Staff on the use of ICT in extension delivery | District wide | Limited access to extension services | No. of staff trained | x | x | x | x | 1,250.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Train women on balanced diet and education on food preservation | District wide | Reduction in mal nutrition | No. of women trained on balance diet and food preservation | x | x | x | x | 3,600.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Organize capacity building on for FBOs and Private Extension Service providers | District wide | Limited capacity of FBOs and Private Extension Service Providers | No. of capacity building programmes organized | x | x | x | x | 3,000.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Promote agribusinesses in the district | District wide | Limited participation in agribusiness | No. of agribusinesses promoted | x | x | x | x | 2500.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Train agro chemical dealers in the district | District wide | Limited capacity in proper usage of agro-chemicals | No. of agro chemical dealers trained | x | x | x | x | 1,000.00 | Dept. of Agric | DA | ||||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Educate Farmers on the proper usage of agro-chemicals | District wide | Limited capacity in proper usage of agro-chemicals | No. of farmers educated | x | x | x | x | 10,000.00 | Dept. of Agric | DA | ||
Economic Development | SP4.2: Agricultural Development | SDG 2,8,9,12
AU 5 |
Conduct disease surveillance and collect data on animals in the district | District wide | Unreliable data | No. of disease surveillance conducted
Type of data collected |
x | x | x | x | 9,000.00 | Dept. of Agric | DA | ||
SDG 2,8,9,12
AU 5 |
Conduct vaccination for livestock and poultry | District wide | Prevent deaths in livestock | No. of vaccination conducted | x | x | x | x | 15,000.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Collect, collate and analyse agricultural data of MRACLS activities for 2020 | District wide | Improved data management | No. of MRACLS activities analyzed | x | x | x | x | 45,000.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Promote direct extension services to farmers/FBOs through regular home and farm visit disseminate improved agricultural deliveries | District wide | Inadequate extension services | No. of extension services promoted | x | x | x | x | 5,000.00 | 15,000.00 | Dept. of Agric | DA | |||
SDG 2,8,9,12
AU 5 |
Undertake monitoring and supervisory visits of selected plan activities in the District by DDO&DDA | District wide | Projects and programmes are monitored | No. of monitoring and supervisory visits undertaken | x | x | x | x | 30,000.00 | Dept. of Agric | DA | ||||
SDG 2,8,9,12
AU 5 |
Organize Farmers Day to acknowledge farmers’ contribution to districts economy | District wide | Deserving farmers are recognized on farmers day | No. of farmers’ Day organized | x | x | x | x | 10,000.00 | 150,000.00 | DA | Dept. of Agric
|
DEVELOPMENT DIMENSION: ENVIRONMENT, INFRASTRUCTURE AND HUMAN SETTLEMENTS
GOAL 4: SAFEGUARD THE NATURAL ENVIRONMENT AND ENSURE A RESILIENT BUILT ENVIRONMENT | |||||||||||||||
PROGRAMMES | SUB-PROGRAMMES | GLOBAL & REGIONAL LINK. | ACTIVITIES | LOCATION | BASELINE | OUTPUT INDICATORS | QUARTERLY TIME SCHEDULE | INDICATIVE
BUDGET GH₵ |
IMPLEMENTING
AGENCIES |
||||||
1 | 2 | 3 | 4 | IGF | GOG
|
DONOR
|
LEAD | COLLAB. | |||||||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP 2.1: Physical Planning
|
SDG 9, 11, 15,17
AU 1, 10, 11,12 |
Conduct regular Site inspections | District wide | Occurrence of unauthorised development | No. of regular site inspection conducted | x | x | x | x | 5,000.00 | PPD | DA
|
||
Digitize Old layouts of Selected Communities | District wide | Use of manual layouts | No. of old layouts of communities digitized | x | x | x | x | 5,000.00 | PPD | DA | |||||
Organize Routine Building Inspection | District wide | Occurrence of unauthorised development | No. of inspection organised monthly | x | x | x | x | 16,000.00 | PPD | DA
DWD |
|||||
Prepare 4 new layouts | Aduasa, Swedru, Awisa, Apaaso | Inadequate number of layouts | No. of layouts prepared | x | x | x | x | 20,000.00 | PPD | DA | |||||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP2.2: Infrastructure Development
; |
SDG 2, 9,17
AU 10, 11,12 |
Construct 3 No. Culvert in flood prone communities
|
Swedru Suame
Mensakrom Awisa Pentecost
|
Limited access to flood prone areas | No. of Culverts constructed | x | x | x | x | 400,000.00
|
DWD | Feeder Roads
Dept. of Highways |
||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP2.2: Infrastructure Development
; |
SDG 2, 9,17 AU 10, 11,12 | Construction/Rehabilitation / reshaping of selected roads | Akortekrom-
Akim oda- Amanfopong Swedru and Awisa Township roads |
Poor state of existing roads | Length of roads reshaped | x | x | x | x | 100,000.00
|
HW, FR DWD | DA,MP | ||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP2.2: Infrastructure Development
; |
SDG 2, 9,17 AU 10, 11,12 | Extension of electricity to newly developed areas
|
Adeeto
Awisa Apoli-Ningo |
Expansion in the existing settlements | No. of beneficiary communities | x | x | x | x | 7,000.00 | ECG | DWD | ||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP2.2: Infrastructure Development
; |
SDG 2, 9,17 | Rehabilitation and maintenance of Street lights in all Communities | District wide | Poor functioning of street lights | No. of Street lights rehabilitated | x | x | x | x | 100,000.00 | DWD | DA | ||
INFRASTRUCTURE DELIVERY AND MANAGEMENT | SP2.2: Infrastructure Development
; |
AU 10, 11,12 | Complete 2 No. durbar grounds | Apoli
Asawase |
Poor state of existing facility | No. of durbar grounds completed | x | x | x | 300,000.00 | MDA | MP
DA
|
|||
Environmental &Sanitation Management | Management SP5.1:Disaster Prevention & Mgt | Organize Sensitization campaigns to popularize and promote climate change responses as well as climate resilience practices | District wide | Low awareness created | No. of sensitization campaigns organized | x | x | x | 10,000.00 | NADMO | DA | ||||
Environmental &Sanitation Management | Management SP5.1:Disaster Prevention & Mgt | SDG 1, 2, 11, 13, 16,17
AU 5, 7, 11,12 |
Organize zonal tours to monitor disaster prone areas in the district annually | District wide | Regular activity carried out | No. of zonal tours organized | x | x | x | x | 4,000.00 | NADMO | DA | ||
SDG 1, 2, 11, 13, 16,17
AU 5, 7, 11,12 |
Organize public education on floods, Epidemics, Rains, windstorm, domestic fire and bushfires | District wide | Routine activity carried out | No. of public education organized | x | x | x | x | 3,200.00 | NADMO | DA | ||||
Environmental &Sanitation Management | Management SP5.1:Disaster Prevention & Mgt | SDG 1, 2, 11, 13, 16,17
AU 5, 7, 11,12 |
Formation and training of disaster volunteer groups
(DVGs) |
District wide | Inadequate existing DVG’s | No. of DVGs formed | x | x | x | x | 8,000.00 | NADMO | DA | ||
Environmental &Sanitation Management | Management SP5.1:Disaster Prevention & Mgt | Desilting of choked gutters | District wide | Prevention of flood disaster | No. choked gutters disilted | x | x | x | x | 1,200.00 | NADMO | DA | |||
Environmental &Sanitation Management | Management SP5.1:Disaster Prevention & Mgt | Organize Disaster platform committee members meeting | District wide | Regular activity carried out | No. of platform committee meeting organized | x | x | x | x | 25,000.00 | NADMO | DA | |||
Environmental &Sanitation Management
Environmental &Sanitation Management |
Management SP5.1:Disaster Prevention & Mgt
SP 5.2: Natural Resource Conservation |
SDG 13,15,16,17
AU 7,12 |
Collaborate with Forestry Commission to Plant trees to serve as windbreak in selected communities | District wide | Prevention of disaster | No. of trees planted | x | x | x | x | 20,000.00 | NADMO | DA | ||
SDG 13,15,16,17
AU 7,12 |
Arrest and prosecute illegal chain saw operators and wood dealers
|
District wide | Increasing number of illegal wood operators | No. of offenders prosecuted | x | x | x | x | 5,000.00 | FC | DA, GPS | ||||
SDG 13,15,16,17
AU 7,12 |
Reforest 200 hectares of degraded forest
|
District wide | Increasing forest degradation | Hectares of degraded forest recovered | x | x | x | x | 25,000.00 | FC | DA | ||||
Environmental &Sanitation Management | SP 5.2: Natural Resource Conservation | SDG 13,15,16,17
AU 7,12 |
Engage forest fringe communities to plant food crops alongside tree seedlings to augment their income and boost reforestation. | Apoli, Ningo, Aduasa, Kroboase, Akortekrom, | Limited capacity of community members | No. of communities engaged | x | x | x | x | 15,000.00 | FC | DA | ||
Environmental &Sanitation Management | SP 5.2: Natural Resource Conservation | SDG 13,15,16,17
AU 7,12 |
Educate/ Sensitise fringe communities on forest conservation
|
District wide | Increasing forest degradation | No. of communities educated | x | x | x | x | 10,000.00 | FC | DA | ||
Environmental &Sanitation Management | SP 5.2: Natural Resource Conservation | SDG 13,15,16,17
AU 7,12 |
Conduct daily inspection in the forest reserves to prevent encroachment and illegal lumbering | District wide | Increasing forest degradation | No. of inspections organized | x | x | x | x | 4,000.00 | FC | DA | ||
Environmental &Sanitation Management | SP 5.2: Natural Resource Conservation | SDG 13,15,16,17
AU 7,12 |
Celebration of annual world tree planting day | District wide | Annual activity carried out | World tree planting day observed | x | x | x | x | 5,000.00 | FC | DA
|
||
Environmental &Sanitation Management | SP 5.2: Natural Resource Conservation | SDG 13,15,16,17
AU 7,12 |
Monitor activities of small scale miners and organize training on land reclamation and environmental sustainability for small scale miners | District wide | Lack of capacity to undertake environmentally sustainable measures | No. of small scale miners trained | x | x | x | x | 4,500.00 | FC | DA |